The year 2005 ...


The new multi-media complex of Argent-sur-Sauldre opened its doors to the public mid-May.
This centre can been used as a showroom, cinema and theatre.

Characteristics:
Client: City of Argent-sur-Sauldre
Surface : 495 m2
Beginning of the building site: May, 17 2004
End: April, 28 2005

January - March 2005 :
External works: Development of the external accesses

Décembre 2004:
Gros oeuvre: Phase finale
Enduit et habillage en plaquettes de briques terminés
Menuiseries extérieures: pose des menuiseries alu. terminée
Electricité: cablage éléctrique réalisé à 80%.

September / October 2004:
Roofing:finished
Characteristics: Traditional sawn timber frame. Natural slate roofing. Insulation reinforced
September / October 2004:
Civilworks : Final phase
UIMM : End of building site...

The construction of the new offices of the UIMM was finished in September.

The Inauguration of the UIMM took place on September 9, 2005 at 3:00 pm

Characteristics:
Client: UIMM du Cher
Surface SHON: 230 m2
Cost: 279 700 € HT
Beginning of the building site: September 15, 2004
End: March 3, 2005
December 2004
Civilworks: Finished tightness - Cladding carried out at 80%.
Exterior joineries: Realized to 50%
September/October 2004
Civilworks: Work of masonry has just begun.
Characteristic: The building will present a metal frame.
“Cours Beauvoir" Street ...


After the destruction of several houses "Cours Beauvoir" street in Bourges, 22 social housings were built.

Extension and refitting of the offices from the Texrod company in Bourges

Characteristics :
Client : TEXROD
Surface : 131 m2
Cost : 306 000 € except external works
Beginning of the building site: April 6, 2005
End of building site : August 31, 2005