Construction of 9 houses and 2 collectives Les Franges de Merlattes in Bourges (18000)
Beginning of the building site: September 2007
Delay: 14 mois


Owner : Bourges Habitat
Surface SHON: 1 690 m2.
Estimated cost: 1 657 000 €HT



Extension of a production unit in Vierzon (18100)
Beginning of the building site: February 2008
Construction periods: 8 months


Owner : CALIBRACIER
Surfaces SHON : 2 625 m2
Cost : 2 M€ HT


Réception October 2008:

> more




Beginning of the building site: January 2007
End of building site: January 2007





Extension and renovation of premises of the city hall to Allouis (18500)
Beginning of the building site: January 2009
Construction periods: 12 months


Client: Mairie d'Allouis
Surfaces SHON : 551 m2.
Cost : 544 k€ HT


> more



Construction of a Laboratory of medical analyses to Saint-Doulchard (18230)
Beginning of the building site : November 12, 2007
Delay : 8 months


Client: Private
Surface SHON: 916 m2.
Estimated cost: 1 167 000 € HT
> more



Realization of 17 individual residences in Saint-Doulchard (18230)
Beginning of the building site: March 8, 2006
Times: 14 months


Owner: OPHLM du Cher
Localization: "le cou d'âne" in Saint-Doulchard
Surfaces SHON: 1 637 m2.
Estimated cost: 1 131 400 €.
> more


Barrack buildings of Rosnay (36)
Beginning of the building site: June 28, 2006
Times: 2 x 8 months


Program : Modernization of barrack buildings: Redistribution of the buildings and reorganization of the rooms.
Owner: Ministry for Defense and the Navy
Surfaces to be treated: 2 669 m2.
Estimated cost: 2 974 000 euros.



Rénovation of FAE to Bourges (18000) after a fire
Beginning of the building site: January 2009
Construction periods: 6 months


Client : Ministry of Justice - DRPJJ
Surfaces SHON : 638 m2
Cost : 497 k€ HT


> more



Construction of a canteen to the elementary school of Saint-Caprais
Beginning of the building site: April 2008
Construction periods: 8 months 1/2


Client : Town hall of Saint-Caprais
Surfaces SHON : 190 m2
Cost : 403 k€ HT
Réception Janvier 2009 :

> more


Construction of a cloakroom for the stage of football to Méry-es-Bois (18380)
Beginning of the building site: Febrary 2008
Delays: 5 months


Owner: Town hall of Méry-es Bois
Program: Creation and construction of a new cloakroom for the stage of football .
Surfaces SHON: 143 m2.
Estimated cost: 178 000 € H.T.



Construction of residences in Guerche/l'Aubois(18150)
Beginning of the building site: September 2007
Delay: 12 months


Construction of 15 residences :
Owner: OPHLM du Cher
Surfaces SHON: 1 263 m2.
Estimated cost: 1 000 000 € HT




Beginning of the building site: November 25, 2005
End of building site: March 2007


Owner: OPHLM du Cher
Localization: Chemin de Saint-Marc to Argent-sur-Sauldre
Surfaces SHON: 2 526 m2.
Estimated cost:1 752 580 € HT.



Banks of France: Nevers - Orléans - Bourges - Blois - Auxerre


Mission: Maintenance and realization of technical work within the Banks of France of the towns of Nevers, Orleans, Blois, Auxerre and Bourges.